Swissotel Sydney

Swissotel appointed SHAPE to complete a 5-star refurbishment to compete with other leading corporate hotels in Sydney.

Client: GL Investments
Designer: CHADA
Delivery Model: Lump Sum
Location: Sydney, NSW
Duration: 47 weeks
Project Size: 15, 401 m2

Building in a live environment.

Our team completed a refurbishment of level 8 reception, level 10 spa treatment room, 15 levels of corridors and 369 hotel rooms. This included an additional 15 new rooms which were constructed by converting existing space within the hotel.

With at least a 95 per cent occupancy rate during the construction, the early identification and communication of planned noisy works to the client was critical; this ensured potential issues and disruptions due to noise were addressed as quickly as possible.

Related Projects

Undisclosed Tech Client, Sydney Office Fitout

tech-client-sydney-place-shape-australia_1
Undisclosed
NSW
Design & Construction

Zurich Upgrade Works

Zurich Upgrade Works_423105
Zurich Financial Services Australia
NSW
Design & Construction

Government Agency, 255 George St

government-agency-255-george-st-sydney-shape-australia_2
Government Agency
NSW
Fitout & Refurbishment

COX Architecture Sydney Fitout

cox-architecture-sydney-office-fitout-shape-australia_5
COX Architecture
NSW
Fitout & Refurbishment

Undisclosed International Bank Office Fitout

Undisclosed
NSW
Fitout & Refurbishment

SHAPE Sydney Office

SHAPE Australia
NSW
Fitout & Refurbishment

ANZ Workplace Evolution Project

ANZ
NSW
Fitout & Refurbishment

Arnold Bloch Liebler Sydney Offices

Arnold Bloch Liebler
NSW
Fitout & Refurbishment

135 King St Airbridge Removal & Lobby and Facade Upgrades

135-king-st-sydney-lobby-facade-nsw-shape-australia_11
Investa Property Group
NSW
Other Construction

IHACPA L12, 1 Oxford Street Fitout

ihpa-level-12-1-oxford-st-sydney-nsw-shape-australia_3
IHACPA
NSW
SHAPE+