Melton Christian College
SHAPE worked with Cotter Reid Architects to build Toolern Vale campus for Melton Christian College, focusing on inclusivity and durability.
VIC
Modular Construction
melton-christian-college-stage-1-kinglake-shape-australia_8

Client: Melton Christian College
Designer: Cotter Reid Architects
Client Project Manager: H. Troon
Delivery Model: Design & Construct
Location: Toolern Vale, VIC
Duration: Stage 1 – 26 Weeks, Stage 2 – 34 Weeks
Project Size: Building B – 539m2, Building C – 332m2, Building D – 570m2

Delivering a state-of-the-art campus for Melton Christian College

Stage 1:
SHAPE had the fortunate opportunity to work with Cotter Reid Architects to establish the new campus at Toolern Vale for Melton Christian College. Stage One comprised Building B – four flexible General Learning Areas, and Building C – customised for specialist learning, each with its own support areas and amenities.

The reputation of care and kindness that Melton Christian College have established is evident in these buildings. The interior space focuses on inclusivity and accessibility for all with smooth flooring transitions, large open areas, DDA access and hearing augmentation. The high-level architectural details provide modern and appealing aspects both internally and externally, along with functionality for high-traffic areas supported by hard-wearing products. Structurally, the buildings were engineered to provide a permanent solution rather than a relocatable short-term option.

Throughout the project timeline, the external project management team led by Jed Holland of H. Troon accommodated our timeframe, and ensured the necessary requirements were in place for site works to be completed.It’s exciting to see how a greenfield site can be transformed into a functional and appealing educational facility. This was evident on the excited faces of the Prep and Grade One cohort, as well as staff and parents, when they arrived for the commencement of Term 3, 2023.

Stage 2:
After completing Stage 1 – Buildings B and C with Cotter Reid Architects, the Modular by SHAPE team were commissioned to complete Stage 2 at Melton Christian College, Toolern Vale campus. This project comprises Building D which houses four general purpose classrooms fitted with operable walls to adapt to a single contiguous space when required. The scope of works included site preparation, civil services and landscaping.

The modern aesthetic and high-level architecture of Buildings B and C is carried through to Building D. These buildings have been engineered to provide permanent solutions, rather than