Thomson Geer Perth Office Fitout

Upgraded modern and efficient office fitout to accommodate for its expanding business.
thomson-greer-perth-shape-australia_8

Client: Thomson Geer Lawyers
Designer: GlasgowHart
Delivery Model: Design and Construct
Location: Perth, WA
Duration: 16 Weeks (Design Phase), 18 Weeks (Construction Phase)
Project Size: 1,250m2

A collaboration between SHAPE and GlasgowHart delivers a new, multifunctional workspace.

SHAPE were entrusted to deliver the new Perth Office fitout for Thomson Geer, upgrading their Perth office to accommodate for its expanding operations and increased demand for office space.

The project deliverables were to create an upgraded modern and efficient space that aligns with the client’s goals and broader national fitout initiative.

The team collaborated with GlasgowHart to design and develop a multifunctional space that included 43 workstations, bathrooms, staff breakout area, four meeting rooms, reception and waiting area, client kitchen, a dedicated area for printing and collaborative work, as well as specialised communication and AV rooms.

The standout features of the project include timber wall panelling and high-end timber flooring throughout the reception and waiting areas.

From project start-up to post-handover, the project team maintained clear and consistent communication with Thomson Geer, creating a relationship of trust and collaboration.

The project team delivered an exceptional space which improved both the functionality and aesthetic, accommodating staff growth and addressing the previously outdated environment.

Working with the team at SHAPE was an absolute pleasure, and with a busy work schedule, they made the entire process efficient and easy to manage from our perspective. Not only was the job completed on time and to a high standard, but that high standard and professionalism was maintained from start to finish. We would highly recommend SHAPE for any commercial fitout works.

Siobhan Seiuli, Thomson Geer

Related Projects

Clyde & Co Perth Office Fitout

clyde-&-co-perth-office-fitout-shape-australia_1
Clyde & Co
WA
Fitout & Refurbishment

ALS Geochemistry’s New Australian Headquarters and Testing Facility

ALS Geochemistry
WA
New Build

Department of Finance, Parliament Place Fitout

024_P_R_ParliamentHouse2023_PhotographyByMattBiocich B
Department of Finance
WA
Fitout & Refurbishment

KordaMentha Office Fitout

kordamentha-perth-office-fitout-shape-australia_1
KordaMentha
WA
Fitout & Refurbishment

Future Fund Aftercare

future-fund-aftercare-shape-australia_1
Future Fund
NSW
Aftercare

Undisclosed Perth Office Fitout

undisclosed-client-l4-1-william-st-perth-wa-shape-australia_1
Undisclosed
WA
Fitout & Refurbishment

Curtin University B314 Computer Lab Upgrade

b314_curtin_uni_shape_australia_perth_02
Curtin University
WA
Fitout & Refurbishment

Curtin University B405 Clinical Skills Lab Refurbishment Project

b405-curtin-uni-wa-shape-perth-australia_1
Curtin University
WA
Fitout & Refurbishment

Turner & Townsend Office Fitout

turner-&-townsend-office-fitout-perth-wa-shape-australia_1
Turner & Townsend
WA
Fitout & Refurbishment

Department of Communities Office Fitout

department-of-communities-perth-office-fitout-construction-wa-perth-shape-australia_7
Department of Finance
WA
Fitout & Refurbishment