Client: NOUS
Designer: Facilitate
Delivery Model: Fixed-Price Lump Sum
Location: Darwin, NT
Duration: 6 weeks
Project Size: 270 m2
It was a requirement of the project to adhere to the strict time frame, minimise disruptions for tenants, and maintain the existing NABERS energy rating.
The scope of works included the demolition of the existing floor treatments, preparation and painting of existing perimeter walls, columns and new partitions, installation of new meeting rooms, reception area, tea preps, utility areas, breakout areas, back of house and open plan layouts and Mechanical, Electrical, Fire Hydraulic Services
The project was completed during normal working hours, was completed over a 6-week duration, and was delivered on time and defect-free.