Dr Jones & Partners New Clinic
Client:
Dr Jones & Partners
Designer:
BGK Contech
Delivery Model:
Lump Sum
Location:
Seaford Meadows, SA
Duration:
26 weeks
Project Size:
2,300 m2
The facility was designed to incorporate future proofing so it could be reconfigured to fulfil its legacy role as a healthcare provider for the local community.
The new build included a footings redesign due to a high water table and, as the new build required a concrete raft slab, precast panels and structural steel framing needed to be installed.
The fitout component involved:
- Change rooms
- CT room
- Ultrasound rooms (which needed significant lead lining)
To the delight of the client, SHAPE achieved practical completion three months before the original programme. The end result is a flexible and high-quality environment that blends the solidity of their brand.
YOU MIGHT ALSO LIKE
13/12/20
The objective was to improve the line of sight for clinicians to observe patients from within the staff station. To achieve this, existing partitions were removed and replaced with glazed sections. These windows can be switched off when the moment calls for it, allowing for privacy. The scope was then expanded to include a like-for-like rebuild of the perimeter ward area.
21/07/20
The project's objective was to provide ACT Health with a new state-of-the-art Haematology Ward to accommodate 21 patients, largely comprised of single bedrooms and a purpose-built lead-lined Iodine treatment room.
21/06/19
Optus required their Mawson Lakes office to be consolidated to 108 North Terrace, Adelaide.
21/06/19
This project consisted of a new build within the existing SAHMRI North Pod.
21/06/19
SHAPE was engaged by SA Health to procure this project in five stages.
20/06/19
Capital Pathology engaged SHAPE to provide design and build consultation, and to fitout and manage the staged move.
20/06/19
Shape was engaged to undertake the transformation of 2–6 Bowes Street, Woden for new tenants, ACT Health.
20/06/19
SHAPE was engaged by ACT Health to facilitate the decanting of building 15 at Canberra Hospital, located along Yamba Drive, Garran.
20/06/19
This project included a 1,000 m2 expansion to the existing Canberra Hospital emergency department.